Analyze and Design load forecasting for electrical projects
Theory:
According to
load forecasting it is the study of loads, generators and the overall analysis
of practical electrical networks in the form of project before its
implementation is called load forecasting in other words it is the approximate
forecast about the present and future electrical loads which is to be installed
in future. This study tells us about the conductor size, conduit size, power
cables, distribution transformers, generators as well as the flexibility factor
by following the given steps.
Site visit of the location:
In order to
perform precise and accurate load forecasting about the concerned project a
project manager should visit the proposed location where the installation to be
installed by site visit we mean a project manager will go practically
personally on the site he will be responsible to check the existent facility,
availability of electrical power and its distance from the site and other
facilities, like roads, transportation and sewerage system of the location, the
physibility of proposed project with respect of proposed location is the main
responsibility of the project manager.
Land scaling and measurement:
According to
this process a project manager is generally facilitated about the covered area
by the CDA or PDA in the absence of this information and in order for the
precise load forecasting a project manager must know about the land
measurement, in terms of geometry. In according to this step a project manager
may face different types of geometrical shapes in calculation regular and
irregular shapes. For regular shapes already formulas are available and in case
of irregular shapes project manager mush utilize approximation mathematics to
calculate the estimated area of irregular shape, after calculating the area of
any shape expressed in ft square, before performing the third step, load evaluation.
Load evaluation:
According to
this step the defined covered area we mean duly that area where the
construction is to be made not the total area of the land in load evaluation we
take the covered area and multiply it with the load evaluation factor (it is a
factor which determine the type of load in numerical constant) estimated by the
scientist of the related field and the load evaluation factor table represents
the whole information (types of load and other parameters) in numeric form
which is given below;
Load
evaluation Table
S.No
|
Type of load
|
Volt amp per sq
ft
|
1
|
mosque,
auditorium, house, dwelling, churches
|
1
|
2
|
Clubs, courts, hospitals, motels, apartments, Industries,
commercial plazas, restaurant and cinemal houses
|
2
|
3
|
Beauty parlor, barber shops, shops, schools, colleges
And universities
|
3
|
4
|
Govt & private offices
|
3.5
|
5
|
Garages and Godams
|
0.5
|
Demand factor Table:
According to demand factor table it
is a percentage representation of load discussed in load evaluation factor
table this table shows us how much of the covered area should be considered in
terms of percentage of estimated apparent power, represented by S, and this is
the power supplied by the generator should be considered during the design of
load forecasting for the projects given by
Demand factor Table
S.No
|
Types of load
|
Volt
Amp
|
Percentage
|
|
1
2
3
4
|
Dwelling
Hospital
Hotels and motels
All others
|
first
3000
Next
3000-12000
Balance
First
25000
Balance/Remaining
First
20000
Balance/Remainder
Same as
|
100%
35%
25%
40%
40%
or Approx
60%
40%
100%
|
Procedure:
1. First calculated the total area.
2. Then
according to the table I multiplied total area with 3V.A/sq ft.
3. Then subtracted 3000 from total power.
4. Then multiplied total power with 35%.
5. Then added 3000 to total power multiplied by 35%.
6. Then found the phase current by dividing power by 220.
7. Then found current in 3-phase by dividing 440.
Precaution:
·
Save yourself.
·
Save the system.
·
Save the environment.
No comments:
Post a Comment